How to install Your Series 200 Residential Exterior Steel Door & Frame Unit |
|
(1) Prepare the Opening Check the opening dimensions and make sure it is plumb, square and level. If necessary, shim or adjust to correct. CAUTION: This unit is designed to give 1 inch clearance between door bottom and finished floor. For thick carpets or built-up floors, a shim should be installed under the threshold and frame to raise the unit to finish floor level. The installation opening height must be increased to compensate for the shim.
|
![]() |
![]() |
(2) Set the Unit in the Opening Center the unit in the opening and tilt into position. Plumb the hinge side and temporarily |
![]() |
(3) Level and Shim Unit Check the top of door frame to see if door unit is level. If it is not, the correction should be made by placing shims under the jambs and threshold as required.
|
|
(4) Nail the Hinge Side Go outside through another entry and nail through hinge jamb and shims into stud with two(2) 16d galvanized finish nails at each hinge location.
|
![]() |
![]() |
(5) Adjust the Lock Side From the outside, close the door carefully and check to make sure the weatherstrip is sealing against the door from top to bottom and across the top. If necessary, adjust the lock jamb in or out at the top and/or bottom to make sure the unit is sealing properly. (6) Nail the Lock Side From outside, nail through the lock jambs and shims into the stud with two (2) 16d galvanized finish nails as shown. |
(7) Final Steps
|
![]() |
![]() |
(8) Door Bottom Sweep To make sure the door bottom sweep is making contact with the top of the threshold, place a thin piece of paper (such as cellophane) on the threshold and close the door. This piece of paper should pull out with some resistance. If to loose or too tight make adjustment in the height of the threshold. |
(9) Finish Paint Door & Frame
|
|
(10) Double Doors Prepare opening and set unit in the same way as in step one. Shim unit between frame and rough opening behind each hinge.
| ![]() |
![]() |
|
|
(11) Sidelite Units Prepare opening and set unit in the same way as in step one.
| ![]() |
![]() |
|